The Last Planner System Explained

The person who assigns the work on site, the 'last planner', is usually the one who knows whether it can actually be done. This system plans around them.

The Last Planner System (LPS) is a collaborative production planning and control method developed by Glenn Ballard and Greg Howell. It moves from what should be done (the milestone schedule), to what can be done (constraints removed), to what will be done (weekly commitments by the trade foremen), and then measures what did get done, so the team can learn why plans fail.

The five levels of the Last Planner System

LevelHorizonWhoOutput
Master scheduleWhole projectProject leadershipKey milestones
Phase schedule (pull plan)One phase, to a milestoneTrade leaders togetherHandoffs between trades, planned backwards
Lookahead planTypically about six weeksProject team and tradesConstraint log, tasks made ready
Weekly work planNext weekTrade foremen (the last planners)Reliable commitments
Daily huddleTodayCrews and foremenCoordination and quick constraint removal

How to run the Last Planner System

  1. Set milestones in the master schedule.
  2. Pull-plan each phase. Starting at the milestone, each trade states what it needs from the trade before it, working backwards. Agree handoffs and durations in the room.
  3. Run the lookahead. For each task in the window, list its constraints: design information, submittals, materials, equipment, labour, access, prerequisite work, inspections. Assign someone to clear each one by a date.
  4. Make ready. Only tasks with all constraints removed move into the pool of work that can be committed.
  5. Build the weekly work plan. Each foreman commits only to tasks that are ready and that their crew can complete that week.
  6. Hold daily huddles to coordinate and surface new problems.
  7. Measure PPC and record reasons for variance at the end of the week.
  8. Learn and act. Review the most frequent reasons and change the process, not just the next plan.

How to calculate PPC (percent plan complete)

PPC = tasks completed as planned ÷ total tasks planned for the week × 100

Example: the weekly work plan has 40 committed tasks. 34 are fully completed as planned. PPC = 34 ÷ 40 × 100 = 85%.

A task counts only if it's 100% complete. A task that's 90% done counts as not done, because the next trade still can't start. PPC measures how reliable the plan was, not how much work got done.

Typical reasons for variance

Common Last Planner mistakes

Where SpatialSense fits

SpatialSense doesn't run Last Planner; use your pull-planning wall or LPS software for that. It can help with two inputs. When reviewing the weekly plan, a timestamped 360° walk or scan shows whether an area really is complete and handed over, which settles "prerequisite work not complete" arguments with evidence. During the lookahead, constraints found on site can be pinned as issues at their exact location, with an owner and due date.

Frequently asked questions

What is the Last Planner System?

The Last Planner System is a lean construction method for collaborative production planning and control. It links milestone and phase planning to lookahead planning, weekly commitments by trade foremen, and daily huddles, and measures plan reliability with percent plan complete.

Who developed the Last Planner System?

Glenn Ballard and Greg Howell developed it in the 1990s. They went on to found the Lean Construction Institute.

Who is the 'last planner'?

The person who assigns work directly to the crew, usually the trade foreman or supervisor. They are the last person in the planning chain before the work is done.

How do you calculate PPC?

Divide the number of tasks completed as planned by the total number of tasks committed for the week, and multiply by 100. Only fully completed tasks count.

What is a lookahead plan?

A lookahead plan covers the next several weeks, often about six. The team identifies each task's constraints and works to remove them so the task is ready to be committed in a weekly work plan.

Does SpatialSense run the Last Planner System?

No. SpatialSense is a reality-capture platform. It can supply dated visual evidence of whether areas are complete, and track site constraints as pinned issues, alongside your Last Planner process.