Delays in Construction: Types, Causes and Records
Almost every project runs late somewhere. What decides who pays for it is usually the quality of the records kept at the time.
Types of delays in construction
| Type | What it means | Typical result |
|---|---|---|
| Excusable, compensable | Caused by the owner or its team, such as late design information, late access, or owner-directed changes | Extension of time and additional cost |
| Excusable, non-compensable | Caused by neither party, such as exceptional weather or force majeure events, as defined in the contract | Extension of time, usually no additional cost |
| Non-excusable | Caused by the contractor or its subcontractors, such as low productivity, late procurement or rework | No extension; liquidated damages may apply |
| Concurrent | Two or more delays from different parties affecting completion over the same period | Treatment varies by contract and jurisdiction |
| Critical vs non-critical | Whether the delayed activity is on the critical path | Only critical delays move the completion date |
The exact definitions and remedies come from your contract. Standard forms differ on notice periods, what counts as a relevant event, and how concurrent delay is treated.
Common causes of construction delays
- Design and information: incomplete drawings, late RFI responses, slow submittal approvals, design changes.
- Owner issues: late site access, late decisions, late payment, scope changes.
- Contractor issues: poor planning, under-resourcing, subcontractor failure, late procurement, rework from defects.
- Site conditions: unforeseen ground conditions, existing services, contamination.
- External: weather, permits and inspections, supply chain disruption, labour availability.
- Coordination: clashes between trades, especially in MEP-dense areas, discovered late on site.
How delays are analysed
When a delay is disputed, a planner or delay expert analyses the schedule to show what caused the late finish and by how much. Common methods are:
- As-planned vs as-built: compares the baseline schedule with what actually happened. Simple, but weak at showing cause.
- Impacted as-planned: adds delay events into the baseline programme to show their theoretical effect.
- Time impact analysis (TIA): inserts each delay event into the updated schedule at the time it occurred. Often used prospectively to support an extension of time request.
- Windows analysis: divides the project into time periods and analyses the critical path in each.
- Collapsed as-built (but-for): removes delay events from the as-built schedule to show when the work would have finished without them.
Every method depends on knowing what actually happened on site, and when. Guidance such as the Society of Construction Law Delay and Disruption Protocol puts strong emphasis on good contemporaneous records for this reason.
How to manage delays: a practical process
- Keep the schedule updated with actual progress at a regular interval, so the critical path is current.
- Record the site as it is. Daily reports, dated photos, 360° walks or scans of the same areas at regular intervals.
- Give notice on time. Most contracts set a notice period for delay events. Late notice can lose an otherwise valid claim.
- Log the event and its effect: what happened, when, which activities it affected, and the evidence.
- Mitigate. Re-sequence, add resources or work around where reasonable, and record what you did.
- Raise it in the OAC meeting and get the decision or action minuted.
- Prepare the extension of time request with the schedule analysis and the supporting records.
Common mistakes
- Building the story afterwards. Records gathered months later from memory are easy to challenge.
- Photos without dates or locations. They prove something happened, but not where or when.
- Missing notice deadlines.
- A schedule that isn't updated, so nobody can show which activities were critical at the time.
Where SpatialSense fits
SpatialSense doesn't analyse schedules or calculate extensions of time. Where it helps is the record those analyses depend on. Each 360° walk and scan is timestamped when it's added to a project, and Trace walks are GPS-tagged, so a regular capture routine builds a dated visual record of the site as it actually was.
- Show the state of an area on a given date, for example when access was handed over or when a trade finished.
- Compare two dates side by side to show what did, and didn't, progress in between.
- Pin issues at their location, such as an area blocked by another trade, with an owner and a status.
Dated progress records
A sequence of timestamped captures is the record. Construction progress tracking →
360° walks with a timestamp
Who was on site, and what the space looked like, on that date. 360° site documentation →
Compare two dates
See what changed between captures in one view. Compare captures over time →
Site records in Hong Kong
How local teams keep scanning records. Hong Kong site scanning records →
Frequently asked questions
What are the main types of delays in construction?
Excusable compensable delays (caused by the owner), excusable non-compensable delays (caused by neither party, such as exceptional weather), non-excusable delays (caused by the contractor), and concurrent delays where causes from different parties overlap.
What is a concurrent delay?
A concurrent delay is when two or more delay events caused by different parties affect the completion date over the same period. How it is treated depends on the contract and the jurisdiction.
What is the most common cause of delays in construction?
Causes vary by project, but late design information, changes, poor planning, resource shortages and coordination problems are frequently cited. The answer for any one project comes from its own records.
What is a time impact analysis?
A time impact analysis inserts a delay event into the current schedule at the point it occurred and calculates its effect on the completion date. It is often used to support an extension of time request.
What records help prove a construction delay?
An updated schedule, daily reports, correspondence and notices, meeting minutes, and dated, located visual records of site progress, such as photos, 360° walks or scans of the same areas over time.
Can SpatialSense calculate construction delays?
No. SpatialSense doesn't analyse schedules. It provides a timestamped visual record of the site from 360° walks and scans, which supports the schedule analysis your planner or delay expert carries out.
Build the record before you need it. Start a free trial and capture your first timestamped site walk.
14 days free with no credit card, or 30 days free when you book a demo.