Delays in Construction: Types, Causes and Records

Almost every project runs late somewhere. What decides who pays for it is usually the quality of the records kept at the time.

A construction delay is any event that makes work finish later than planned. Not every delay matters equally. A delay to an activity on the critical path pushes back the completion date; a delay to an activity with float may not. Who bears the cost depends on the cause and on the contract.

Types of delays in construction

TypeWhat it meansTypical result
Excusable, compensableCaused by the owner or its team, such as late design information, late access, or owner-directed changesExtension of time and additional cost
Excusable, non-compensableCaused by neither party, such as exceptional weather or force majeure events, as defined in the contractExtension of time, usually no additional cost
Non-excusableCaused by the contractor or its subcontractors, such as low productivity, late procurement or reworkNo extension; liquidated damages may apply
ConcurrentTwo or more delays from different parties affecting completion over the same periodTreatment varies by contract and jurisdiction
Critical vs non-criticalWhether the delayed activity is on the critical pathOnly critical delays move the completion date

The exact definitions and remedies come from your contract. Standard forms differ on notice periods, what counts as a relevant event, and how concurrent delay is treated.

Common causes of construction delays

How delays are analysed

When a delay is disputed, a planner or delay expert analyses the schedule to show what caused the late finish and by how much. Common methods are:

Every method depends on knowing what actually happened on site, and when. Guidance such as the Society of Construction Law Delay and Disruption Protocol puts strong emphasis on good contemporaneous records for this reason.

How to manage delays: a practical process

  1. Keep the schedule updated with actual progress at a regular interval, so the critical path is current.
  2. Record the site as it is. Daily reports, dated photos, 360° walks or scans of the same areas at regular intervals.
  3. Give notice on time. Most contracts set a notice period for delay events. Late notice can lose an otherwise valid claim.
  4. Log the event and its effect: what happened, when, which activities it affected, and the evidence.
  5. Mitigate. Re-sequence, add resources or work around where reasonable, and record what you did.
  6. Raise it in the OAC meeting and get the decision or action minuted.
  7. Prepare the extension of time request with the schedule analysis and the supporting records.

Common mistakes

Where SpatialSense fits

SpatialSense doesn't analyse schedules or calculate extensions of time. Where it helps is the record those analyses depend on. Each 360° walk and scan is timestamped when it's added to a project, and Trace walks are GPS-tagged, so a regular capture routine builds a dated visual record of the site as it actually was.

Dated progress records

A sequence of timestamped captures is the record. Construction progress tracking →

360° walks with a timestamp

Who was on site, and what the space looked like, on that date. 360° site documentation →

Compare two dates

See what changed between captures in one view. Compare captures over time →

Site records in Hong Kong

How local teams keep scanning records. Hong Kong site scanning records →

Frequently asked questions

What are the main types of delays in construction?

Excusable compensable delays (caused by the owner), excusable non-compensable delays (caused by neither party, such as exceptional weather), non-excusable delays (caused by the contractor), and concurrent delays where causes from different parties overlap.

What is a concurrent delay?

A concurrent delay is when two or more delay events caused by different parties affect the completion date over the same period. How it is treated depends on the contract and the jurisdiction.

What is the most common cause of delays in construction?

Causes vary by project, but late design information, changes, poor planning, resource shortages and coordination problems are frequently cited. The answer for any one project comes from its own records.

What is a time impact analysis?

A time impact analysis inserts a delay event into the current schedule at the point it occurred and calculates its effect on the completion date. It is often used to support an extension of time request.

What records help prove a construction delay?

An updated schedule, daily reports, correspondence and notices, meeting minutes, and dated, located visual records of site progress, such as photos, 360° walks or scans of the same areas over time.

Can SpatialSense calculate construction delays?

No. SpatialSense doesn't analyse schedules. It provides a timestamped visual record of the site from 360° walks and scans, which supports the schedule analysis your planner or delay expert carries out.

Build the record before you need it. Start a free trial and capture your first timestamped site walk.

14 days free with no credit card, or 30 days free when you book a demo.