Line of Balance Scheduling: Method, Formula and Example

When the same work repeats floor after floor or kilometre after kilometre, a bar chart hides the thing that matters most: whether each trade is moving at the same speed as the one in front.

Line of balance (LOB) is a scheduling method for repetitive work. It plots each activity as a line on a chart with time on one axis and location or units (floors, houses, road sections) on the other. The slope of each line is that activity's production rate. When lines run parallel, trades follow each other at a steady pace. The method came from manufacturing and production planning and is closely related to location-based scheduling and flowline charts.

When to use line of balance

It suits work where the same sequence of activities repeats across many locations. For one-off, highly varied work, a CPM network schedule is usually the better tool.

How to read a line of balance chart

Line of balance formulas

For one activity, let n = number of units, R = required production rate (units per day), and d = duration for one crew to complete one unit (days).

Worked example

A 20-floor building. The target is to complete one floor of drywall every 2 days, so R = 0.5 floors per day. One drywall crew takes 4 days per floor, so d = 4.

  1. Crews needed = 0.5 × 4 = 2 crews.
  2. Actual rate = 2 ÷ 4 = 0.5 floors per day, which matches the target.
  3. Activity duration = (20 − 1) ÷ 0.5 + 4 = 38 + 4 = 42 days from starting floor 1 to finishing floor 20.

If the trade before drywall runs at 0.4 floors per day, the two lines converge, and drywall will catch up and stall. You either slow drywall to match (fewer crews), speed up the trade ahead, or start drywall later with a bigger buffer so the lines don't meet before the last floor.

How to build a line of balance schedule

  1. Define the repeating unit and the sequence of activities within it.
  2. Estimate the duration per unit for each activity with one crew.
  3. Set the target rate, usually from the handover date or the slowest critical activity.
  4. Calculate crews for each activity to match the target rate as closely as possible.
  5. Add buffers between activities, in time or in units, to absorb variation.
  6. Plot the lines and check for convergence.
  7. Track actual progress by plotting actual completion of each unit against the plan.

Common mistakes

Where SpatialSense fits

SpatialSense doesn't build or calculate line of balance schedules. Where it can help is the actual-progress data. A regular 360° walk or scan of each floor or section, timestamped when it's added to a project, shows which units are really complete on a given date, so the actual lines on the chart come from evidence rather than verbal updates. Comparing two dated captures side by side shows what moved between updates.

Frequently asked questions

What is line of balance in construction?

Line of balance is a scheduling method for repetitive work that plots each activity as a line against time and location. The slope of each line is the activity's production rate, and the aim is to keep lines parallel so trades follow each other steadily.

What is the formula for line of balance?

Crews needed equals the required rate multiplied by the duration per unit for one crew. The time from starting the first unit to finishing the last is (number of units minus 1) divided by the rate, plus the duration per unit.

When should I use line of balance instead of CPM?

Use line of balance where the same activities repeat across many locations, such as typical floors, housing units or road sections. CPM suits one-off work with complex logic. Many projects use both.

What does it mean when lines converge on an LOB chart?

A faster activity is catching up with a slower one ahead of it. When they meet, the faster trade runs out of work and must stop, so rates or buffers need adjusting.

Is line of balance the same as location-based scheduling?

They are closely related. Location-based scheduling builds on line of balance and flowline ideas, adding location breakdown structures and production control.

Can SpatialSense create a line of balance schedule?

No. SpatialSense is a reality-capture platform. It can provide timestamped visual evidence of which units are complete, to feed the actual progress lines in your scheduling tool.

Feed the actual-progress lines with evidence. Start a free trial and capture your first timestamped floor walk.

14 days free with no credit card, or 30 days free when you book a demo.